A house in Mallorca stays cool in summer if you plan the renovation in this order: shade every window from the outside, insulate the roof, make sure air can cross the house at night, leave stone walls and stone floors exposed so they can store the cool, allow for ceiling fans, and install air conditioning only where it is still too warm after all that. What is possible depends on whether you are renovating a finca, a village house or an apartment in Palma. Several of the measures affect the facade or the roof, so they belong in the application to the town hall.
Why mass, shade and moving air cool a house is explained in Natural cooling: keeping a home cool without air conditioning. This article is about the renovation: what works in which house, when it comes up and what needs a permit.
What is possible in a finca, a village house and an apartment
A finca already has the most important thing. The thick rubble-stone walls store a great deal, and the openings are small and set deep in the wall, so the reveal shades part of the glass. The house is detached with windows on all sides, which usually makes cross ventilation easy to arrange. The roof is often the weak point. On rustic land, what you may change on the outside also depends on the municipality and the protection status of the plot.
A village house is narrow and deep and shares its side walls with the neighbours. No sun comes in through those walls. There are windows only at the front and the back, so ventilation runs from the street to the courtyard. A patio, a light shaft and the stair help, because warm air rises and can leave at the top. The heat collects on the top floor, under the roof and under the roof terrace.
In an apartment in Palma you decide the least on your own. The facade and the roof usually belong to the community. For shutters, awnings, different windows or an outdoor unit you need the owners' community as soon as the appearance of the building changes. Inside you have plenty of freedom: plaster, floors, fans and a layout that lets air pass from one facade to the other. More on this in renovating an apartment in Palma. Which building type suits you is compared in finca or townhouse on Mallorca.
Plan the shading together with the windows
The sun has to be stopped before it reaches the glass. So we design shutters and windows as one element and not one after the other. Persianas keep the sun out and let air and softened light through. On the south side a roof overhang or a loggia shades the windows in high summer. In the east and west the sun is low, an overhang does little there, and you need shutters or another vertical screen.
There is glazing that lets less solar heat through. It is useful where external shading is not possible, but it does not replace it. On the terrace, a planted pergola or a tree also shades the wall and the windows behind it. How we plan outdoor space is covered in pool and outdoor living on Mallorca.
Roof and walls: where insulation helps and where it harms
Most of the summer heat enters through the roof. If the roof is being opened in the renovation anyway, that is the moment for good insulation and a pale surface. Both are hard to add later.
With the walls it is the other way round. A thick stone wall cools the room only if it is in contact with it. Internal insulation or a lining wall separates the thermal mass from the room. Damp is the second reason: old stone walls usually sit on the ground without a barrier layer and have to dry out through their surface. So we leave them exposed or plaster them with lime, which is vapour-open. The same goes for floors. Stone, terracotta and tiles are part of the thermal mass, and a thick rug on top takes away their effect.
Ventilation and ceiling fans
Night cooling needs a route through the house. At the design stage we check for every room where the air comes in and where it leaves again. Sometimes it takes no more than moving an internal door or adding a fanlight above it.
A ceiling fan does not lower the air temperature. Moving air feels cooler on the skin, though, and a fan uses little electricity. Fans suit high rooms: in the Arabic Loft in Palma the ceilings are almost five metres high. For the renovation this means the power point, the switch and a fixing in the ceiling that can carry the weight go in during the shell phase, even if the fan itself comes later.
Where air conditioning still makes sense
There are rooms and nights for which all of this is not enough: bedrooms directly under the roof, humid nights on the coast when the air outside hardly cools down, or a house that is fully occupied in August. For those we plan an air-conditioning unit.
Timing matters here. The refrigerant pipes, the condensate drain and the position of the outdoor unit are fixed in the shell phase. The pipes then disappear into walls and ceilings, and the outdoor unit sits where nobody sees or hears it. If you retrofit after the first summer, you get trunking on the plaster. In a finca that is off the mains, cooling also has to be included when the solar system and the storage are sized.
The order during the renovation
- Before you buy or before design starts: record the orientation, the condition of the roof and the existing openings.
- At the design stage: fix windows, shutters, the roof build-up, new openings and the ventilation routes. Decide which rooms get an air-conditioning unit.
- Before the application: put everything that affects the facade, the roof or the structure into the drawings. In an apartment, involve the owners' community.
- In the shell phase: insulate the roof, make the openings, run the wiring and pipes for fans and units.
- In the finishing phase: lime plaster, floors, windows and shutters.
- Outside: pergola and planting.
What needs a permit
On Mallorca the procedure depends on whether the work needs an architect's project. Simple interior works such as new floors or painting run through a notification to the town hall, the comunicación previa. In Palma, work on the exterior design needs a technician's signature, and you may only start 15 calendar days after filing. As soon as the structure, the volume or the facade changes substantially, you need a building licence, the licencia urbanística.
On protected buildings and on protected rustic land a notification is never enough. Other municipalities have their own rules. For shutters, replacement windows, a pergola and an outdoor unit we therefore always ask the town hall in question before we design. The procedures are set out in building permits on Mallorca: obra menor and obra mayor.
How we plan this at CARLO Design
In the design we plan shading, roof, ventilation and services together and clarify with the town hall which of them belongs in which application. What a renovation costs overall is covered in finca renovation costs on Mallorca. How we work is on renovation on Mallorca and interior design on Mallorca.
FAQ
How do I keep a finca in Mallorca cool without air conditioning?
With external shading on every window, an insulated roof and ventilation at night. The thick stone walls of a finca store the cool of the night as long as they are not lined on the inside. Ceiling fans help on the days when that is not enough. Whether a unit is still needed after that depends on the house and on how you use it.
Do I need a permit for shutters or an awning?
Both change the outside of the house, so ask the town hall before fitting them. In Palma, exterior design runs through a notification signed by a technician. On protected buildings and on protected rustic land a notification is never enough. In an apartment the owners' community also has to approve if the appearance of the facade changes.
Should I insulate thick stone walls on the inside?
For summer heat, usually not. Internal insulation separates the wall from the room, and the wall can then no longer pass the cool of the night on to the room. Old stone walls also need to dry out through their surface. Insulation belongs on the roof first.
Are ceiling fans enough instead of air conditioning?
In a well-shaded house with an insulated roof, often for most of the summer. A fan does not lower the air temperature, but moving air feels cooler on the skin, and a fan uses little electricity. For bedrooms under the roof or for humid nights an air-conditioning unit can still make sense.
When in the renovation do I have to decide about cooling?
At the design stage, before the application goes to the town hall. Windows, shutters, the roof build-up and new openings are in the drawings, and the wiring and pipes for fans and air-conditioning units go in during the shell phase. If you decide after plastering, you get visible cable trunking.